Question: For the project given below: how long is the project expected to take ( all values given are in weeks ) and what is the

For the project given below: how long is the project expected to take (all values given are in weeks) and what is the variance of the critical path? What is the probability the project will require 12 weeks or less?
Immediate Optimistic Most Likely Pessimistic Activity Predecessors Time (a) Time (m) Time (b)
A B C D E F -
A
A
A B,C,D E 1.52.50.40.51.00.5 2.03.50.51.03.01.0 5.55.50.64.58.01.5