For the project given in the attached table; 1- Draw the AON diagram for the project. In
No answer yet for this question.
Ask a Tutor
Question:
For the project given in the attached table;
1- Draw the AON diagram for the project. In the diagram all calculations for ES, EF, LS and LF should be performed
2- Calculate the total and free float for each activity and determine the critical path.
3- Re-perform all calculations using a spread sheet (MS Excel) and compare the calculations resulted from the AON diagram.
4- Draw a Gaunt Chart for the project plan