Question: For the project with the activates and costs given below Draw the network Calculate the CP The slacks for each activity The project cost Project

  1. For the project with the activates and costs given below
  1. Draw the network
  2. Calculate the CP
  3. The slacks for each activity
  4. The project cost
  5. Project cost with most aggressive schedule
  6. Probability that the project could finish in 31 days
  7. 95% confidence for project completion time

Activity

Predecessor

Optimistic Duration

Normal Duration

Pesimistic Duration

Normal Cost

Crash time

Crash Cost

A

NA

4

5

6

$ 300.00

5

$ 300.00

B

A

5

8

9

$ 250.00

5

$ 400.00

C

A

2

2

3

$ 100.00

2

$ 100.00

D

A

3

6

7

$ 300.00

3

$ 600.00

E

B,C

2

3

5

$ 150.00

2

$ 300.00

F

C,D

3

4

6

$ 275.00

3

$ 300.00

G

E,F

8

9

12

$ 700.00

8

$ 900.00

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!