Question: For the projects described in Tables 1 0 - 2 0 and 1 0 - 2 1 , respectively, suggest a project schedule that would

For the projects described in Tables 10-20 and 10-21, respectively, suggest a project schedule that would complete the project in minimum time and result in relatively constant or level requirements for labor over the course of the project.
TABLE 10-20
Activity A B C D E F G H I J K
Predecessors --------- A B B C C D,E F,G H
Duration 35117643643
Workers Per Day 9641016958237
TABLE 10-21
Activity A B C D E F G H I J K L M N
Predecessors --------- A A A B B C F,G H,I,L F,G D,J E,K
Duration 51726432645145
Workers Per Day 0309542141041273