Question: For the projects described in Tables 1 0 - 2 0 and 1 0 - 2 1 , respectively, suggest a project schedule that would
For the projects described in Tables and respectively, suggest a project schedule that would complete the project in minimum time and result in relatively constant or level requirements for labor over the course of the project.
TABLE
Activity A B C D E F G H I J K
Predecessors A B B C C DE FG H
Duration
Workers Per Day
TABLE
Activity A B C D E F G H I J K L M N
Predecessors A A A B B C FG HI,L FG DJ EK
Duration
Workers Per Day