Question: QUESTION 4 [8] The baseline time estimate for the completion of a sports field at centurion primary is 20 weeks and the baseline cost estimate
![QUESTION 4 [8] The baseline time estimate for the completion of](https://s3.amazonaws.com/si.experts.images/answers/2024/07/668b90ad67bc2_572668b90ace319f.jpg)
QUESTION 4 [8] The baseline time estimate for the completion of a sports field at centurion primary is 20 weeks and the baseline cost estimate is R100 000. Assume that the risk likelihood for the project is 0.3 , if the risk is materialized the project would be delayed by 6 weeks and it will cost R 20000 more. 4.1. Calculate risk time (RT) (2) 4.2. Risk cost (RC), (2) 4.3. Expected project completion time (ET) (2) 4.4. Expected project completion cost (EC). (2)