Question: For the schedule below, draw a Gantt chart and then find the critical path for the activity. table [ [ table [ [

For the schedule below, draw a Gantt chart and then find the critical path for the activity.
\table[[\table[[Activity],[Code]],Activity Description,\table[[Depends],[on]],Level,\table[[Duration],[(Day)]]],[100,Inspect the machine after installation,300,4,1],[200,Hire the operator,None,1,25],[300,Install the new machine,500,400,3,2],[400,\table[[Insect and store the machine after],[delivery]],700,2,1],[500,Hire labor to install the new machine,None,1,20],[600,Train the operator,200,300,4,3],[700,Order and deliver the new machine,None,1,30]]