Question: Given the following project to landscape a new building site, (a) Draw a Gantt chart using MSP. (b) Find the critical path and project duration
.png)
(a) Draw a Gantt chart using MSP.
(b) Find the critical path and project duration in days.
(c) Given that each resource is assigned 100% to each task, identify the resource constraints.
(d) Level the resources and determine the new project duration and critical path.
(e) Identify what alternative solutions can be used to shorten the project duration and not over-allocate theresources.
Activity Immcdiat Duration Rcsource Predecessor (days) Activi A: Get plants B: Get flowers C: Obtain soil D: Obtain B. C XY E: Select labor F: Set date G: Begin E, F XY
Step by Step Solution
3.35 Rating (164 Votes )
There are 3 Steps involved in it
The Gantt chart with critical path A C D E G in red looks like this The Resource Usage View from Mic... View full answer