Question: For the schedule developed using Johnson's rule, the total length of time taken to complete the seven printing and binding jobs ( including binding )

For the schedule developed using Johnson's rule, the total length of time taken to complete the seven printing and binding jobs (including
binding)=60 hours (enter your response as a whole number).
d) What is the idle time in the binding shop, given the optimal solution?
The idle time in the binding shop based on the sequence developed using Johnson's rule = hour(s)(enter your response as a whole