Question: ( For your answers use 2 decimal places ) . You are very close to reach the time limit to finish your project without paying
For your answers use decimal places
You are very close to reach the time limit to finish your project without paying penalty fees. The duration of a critical activity for this project is not easily estimated. You have the following statistical information:
Based on your PM expertise, you decided that the best way to estimate the duration of this activity is using the Threepoint Estimate with a Beta Distribution.
What is the estimated activity duration? Answer Question