Question: For your project drug - testing project, you estimate that each lab technician will need to commit 3 6 hours a week to the project.

For your project drug-testing project, you estimate that each lab technician will need to commit 36 hours a week to the project. What does this figure translate to at 75 percent efficiency/100 percent availability?
(A)18 hours
 For your project drug-testing project, you estimate that each lab technician