Question: For your Project the earned value = $380. The actual cost =$650. The planned value =$360. The total project budget is $700. Assume the current

For your Project the earned value = $380. The actual cost =$650. The planned value =$360. The total project budget is $700. Assume the current variances are a typical and that the remaining work will be completed using original estimates. What is the project's estimate at completion