Question: For your project the earned value = $450. The actual cost = $280. The planned value = $600. The total project budget is $1200. Assume

For your project the earned value = $450. The actual cost = $280. The planned value = $600. The total project budget is $1200. Assume the original estimate was flawed. Your engineering team has given you a new estimate for the remaining work of $1900. What is the project's estimate at completion
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
