Question: For your project the earned value = $450. The actual cost = $280. The planned value = $600. The total project budget is $1200. Assume

For your project the earned value = $450. The

For your project the earned value = $450. The actual cost = $280. The planned value = $600. The total project budget is $1200. Assume the original estimate was flawed. Your engineering team has given you a new estimate for the remaining work of $1900. What is the project's estimate at completion