Question: For your project you are developing a web site which is estimated to take 160pw of effort. Your plan is to follow the Agile process

For your project you are developing a web site which is estimated to take 160pw of effort. Your plan is to follow the Agile process with:

  • 3-teams
  • 4-engineers per team
  • Use 5-sprints
  • Each sprint to take 3-weeks

Your boss says: time is of essence; you need to accelerate the project and complete it in 12-weeks if you need, you can spend more money.

Questions:

  1. (3pt) Based on your plan, how long would the project take?
  2. (4pt) Would you consider Fast Tracking or Crashing?
  3. (10pt) Figure out a way to reduce the project time as your boss wants without changing the scope.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!