Question: For your project you are developing a web site which is estimated to take 160pw of effort. Your plan is to follow the Agile process
For your project you are developing a web site which is estimated to take 160pw of effort. Your plan is to follow the Agile process with:
- 3-teams
- 4-engineers per team
- Use 5-sprints
- Each sprint to take 3-weeks
Your boss says: time is of essence; you need to accelerate the project and complete it in 12-weeks if you need, you can spend more money.
Questions:
- (3pt) Based on your plan, how long would the project take?
- (4pt) Would you consider Fast Tracking or Crashing?
- (10pt) Figure out a way to reduce the project time as your boss wants without changing the scope.