Question: FORMATIVE ACTIVITY 16: PROJECT IMPLEMENTATION Answer all the questions below [Total: 15] 1. Explain the statement, Critical tasks have zero float. (3) 2. Explain the
FORMATIVE ACTIVITY 16: PROJECT IMPLEMENTATION
Answer all the questions below [Total: 15]
1. Explain the statement, Critical tasks have zero float. (3)
2. Explain the significance of critical and non-critical tasks. (3)
3. Explain the concept of float. (3)
4. Identify the tools used at your organisation to highlight the critical path of your projects. Do different divisions use the same tools? How does the use of these tools influence project delivery at your organisation? (6)