Question: Formulae: Expected time, E- (0+4'M+P/6 Time estimates (in weeks) for Milkwaukee Paper's Project. Review the expected times and variances for all of the activities in

Formulae: Expected time, E- (0+4'M+P\/6 Time
Formulae: Expected time, E- (0+4'M+P\/6 Time estimates (in weeks) for Milkwaukee Paper's Project. Review the expected times and variances for all of the activities in the project. Optimistic, Most Likely, Pessimistic, Expected Variance, [(p. Activity 0 M P Time, E O\/6]^2 A 1 2 3 B 2 3 4 1 2 3 D 2 4 6 E 1 4 7 1 2 9 G 3 4 11 H 1 2 3