Question: FORWARD PASS AND BACKWARD PASS ACTIVITY ES EF LS LF SLACK CRITICAL A 0 4 0 4 0 YES B 0 3 1 4 1

FORWARD PASS AND BACKWARD PASS
ACTIVITY
ES
EF
LS
LF
SLACK
CRITICAL
A
0
4
0
4
0
YES
B
0
3
1
4
1
C
4
9
4
9
0
YES
D
3
7
6
10
3
E
9
13
9
13
0
YES
F
13
20
14
21
1
G
13
19
13
19
0
YES
H
20
24
21
25
1
I
7
16
10
19
3
J
19
25
19
25
0
YES
CRITICAL PATH = A--C--E--G--J
DURATION OF CRITICAL PATH =25
Explanation:
ES = Max(EF Of All Predecessors); 0 For The First Activity
EF = ES + Duration
LF = Min(LS Of All Successor Activities); Max EF As LF For Last Activity
Slack = LF - EF or LS - ES
Critical Path = Longest Path With 0 Slack

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!