Question: Problem 2) The AON network for the project is provided, along with information on the normal time, crash time, normal cost, and crash cost, as
Problem 2)
The AON network for the project is provided, along with information on the normal time, crash time, normal cost, and crash cost, as well as the earliest start time (ES), earliest finish time (EF), latest start time (LS), latest finish time (LF), and slack time for each activity.
| Activity | Immediate predecessors | Normal time (days) | Crash time (days) | Normal cost | Crash cost | Crash cost per day |
| A | - | 2 | 2 | 400 | - | - |
| B | A | 7 | 7 | 800 | - | - |
| C | A | 5 | 2 | 600 | 900 | 100 |
| D | A | 4 | 1 | 1600 | 2200 | 200 |
| E | C, D | 4 | 1 | 500 | 1700 | 400 |
| F | B, E | 2 | 2 | 1300 | - | - |
| Activity | ES | EF | LS | LF | Slack time |
| A | 0 | 2 | 0 | 2 | 0 |
| B | 2 | 9 | 4 | 11 | 2 |
| C | 2 | 7 | 2 | 7 | 0 |
| D | 2 | 6 | 3 | 7 | 1 |
| E | 7 | 11 | 7 | 11 | 0 |
| F | 11 | 13 | 11 | 13 | 0 |

Use this information to complete this question: Crash the above project to the maximum days it can be crashed at the least cost. For each stage (day) that the project is crashed, fill out the following table. If more rows are needed, please add them manually.
| Stage | Critical path/s | Total project time before crashing | Crash activity/ies | Crash cost added | Total crash cost of the project | Total project time after crashing |
| 1 |
| |||||
| 2 |
| |||||
| 3 |
|
What happens to the slack time of activity B if the duration of activity C reduced by 2 days? Explain your answer.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts