Question: Problem 2) The AON network for the project is provided, along with information on the normal time, crash time, normal cost, and crash cost, as

Problem 2)

The AON network for the project is provided, along with information on the normal time, crash time, normal cost, and crash cost, as well as the earliest start time (ES), earliest finish time (EF), latest start time (LS), latest finish time (LF), and slack time for each activity.

Activity Immediate predecessors Normal time (days) Crash time (days) Normal cost Crash cost Crash cost per day
A - 2 2 400 - -
B A 7 7 800 - -
C A 5 2 600 900 100
D A 4 1 1600 2200 200
E C, D 4 1 500 1700 400
F B, E 2 2 1300 - -

Activity ES EF LS LF Slack time
A 0 2 0 2 0
B 2 9 4 11 2
C 2 7 2 7 0
D 2 6 3 7 1
E 7 11 7 11 0
F 11 13 11 13 0

Problem 2) The AON network for the project is provided, along with

Use this information to complete this question: Crash the above project to the maximum days it can be crashed at the least cost. For each stage (day) that the project is crashed, fill out the following table. If more rows are needed, please add them manually.

Stage Critical path/s Total project time before crashing Crash activity/ies Crash cost added Total crash cost of the project Total project time after crashing
1

2

3

What happens to the slack time of activity B if the duration of activity C reduced by 2 days? Explain your answer.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!