Question: Forward scheduling is the scheduling of: A . the final operation first beginning with the due date. B . the start items or component parts.

Forward scheduling is the scheduling of:
A. the final operation first beginning with the due date.
B. the start items or component parts.
C. jobs as soon as the requirements are known.
D. the end items or finished products.
E. jobs according to their profit contributions.