Question: Four jobs must be processed on a single machine. The time required to process each job and the date the job is due are shown

Four jobs must be processed on a single machine. The time required to process each job
and the date the job is due are shown in Table 63. The delay of a job is the number of
days after the due date that a job is completed (if a job is completed on time or early, the
job's delay is zero). In what order should the jobs be processed to minimize the total de-
lay of the four jobs?
TABLE 63
Durations and Due Date of Jobs
 Four jobs must be processed on a single machine. The time