Four trucks, 1, 2, 3, and 4, are waiting on a loading dock at XYZ Company that
Fantastic news! We've Found the answer you've been seeking!
Question:
Four trucks, 1, 2, 3, and 4, are waiting on a loading dock at XYZ Company that has only a single service bay. The trucks are labeled in the order that they arrived at the dock. Assume the current time is 1:00 p.m. The times required to unload each truck and the times that the goods they contain are due in the plant are given in the following table.
Truck | Unloading Time (minutes) | Time Material Is Due |
1 | 20 | 1:25 p.m. |
2 | 14 | 1:45 p.m. |
3 | 35 | 1:50 p.m. |
4 | 10 | 1:30 p.m. |
Determine the schedules that result for each of the rules FCFS, SPT, EDD, and CR. In each case compute the mean flow time, average tardiness, and a number of tardy jobs.