Question: Frazier Fudge, Inc. is considering 2 mutually exclusive projects with the following cash flows. Which project should be accepted? Assume a cost of capital of
Frazier Fudge, Inc. is considering 2 mutually exclusive projects with the following cash flows. Which project should be accepted? Assume a cost of capital of 10%.
| Years | Project X | Project Y |
| 0 | ($350) | ($350) |
| 1 | $130 | $200 |
| 2 | $150 | $120 |
| 3 | $180 | $120 |
| a. | Project X because NPV is $27.4 |
| b. | Project Y because NPV is $31 |
| c. | Project X because IRR is 13.7% |
| d. | Project Y because IRR is 12.2% |