Question: Free float is the: Group of answer choices Difference between the early finish dates and the late finish dates of an activity Difference in the
Free float is the: Group of answer choices Difference between the early finish dates and the late finish dates of an activity Difference in the float value of the critical path activities and the float value of the specific activity being analyzed Amount of time an activity can be delayed without impacting the early start of the successor activity Difference between the early dates and late dates of an activity