Question: The critical path method ( CPM ) calculates the theoretical early start and finish dates and late start and finish dates. The difference between the
The critical path method CPM calculates the theoretical early start and finish dates and late start and finish dates. The difference between the late and early start of a task is a:
Group of answer choices
Total float
Free float
Feeding buffer
Danger zone