Question: Freegen is making a complex product for the first time. If it takes 3,000 hours to make the first one and their customer wants 8

Freegen is making a complex product for the first time. If it takes 3,000 hours to make the first one and their customer wants 8 units in total, how long does it take to make all 8 if an 80% cumulative average time learning curve is appropriate? A 21,600 hours B 16,441 hours 15,652 hours D 15,552 hours