Question: From question #1, what is the EF for Node E? A) 25 B)26 C)27 D)28 From question #1, what is the LF for Node E?

From question #1, what is the EF for Node E?
A) 25
B)26
C)27
D)28
From question #1, what is the LF for Node E?
A)19
B)24
C)25
D)26
What is the critical path from #1?
A) A~B~E~F~G
B) A~B~E~G
C) A~B~C~D~F~G
D) A~C~E~G
From question #1, what is the EF for Node D?
A)19
B)20
C)21
D)22
From question #1, what is the ES for Node E?
A)18
B)19
C)20
D)25
From question #1, what is the LS for Node C?
A)9
B)10
C)19
D)20
From question #1, what is the slack in node E?
A) 0 days
B) 2 days
C) 3 days
D) 4 days
From question #1, what is the LF for Node D?
A) 18
B) 19
C) 21
D) 22
From question #1, what is the slack in node D?
A) 0 days
B) 1 day
C) 2 days
D) 4 days
From question #1, what is the ES for Node C?
A) 3
B) 4
C) 5
D) 6
We have a project (Cardinal), with these activities in days: Activity A with duration 4 and no precedents. Activity B with duration 15 and predecessor. A, Activity C with duration 9 and predecessor. A, Activity D with duration 2 and predecessor B, Activity E has duration 6 and predecessors B and C, Activity F has duration 4 and predecessor D, and Activity G has duration 15 and predecessors of E and F. Draw this to answer the following questions. How long is this project scheduled to take? 34 days 37 days 40 days 41 days