Question: From question #1, what is the EF for Node E? A) 25 B)26 C)27 D)28 From question #1, what is the LF for Node E?

From question #1, what is the EF for Node E? A)

From question #1, what is the EF for Node E?

A) 25

B)26

C)27

D)28

From question #1, what is the LF for Node E?

A)19

B)24

C)25

D)26

What is the critical path from #1?

A) A~B~E~F~G

B) A~B~E~G

C) A~B~C~D~F~G

D) A~C~E~G

From question #1, what is the EF for Node D?

A)19

B)20

C)21

D)22

From question #1, what is the ES for Node E?

A)18

B)19

C)20

D)25

From question #1, what is the LS for Node C?

A)9

B)10

C)19

D)20

From question #1, what is the slack in node E?

A) 0 days

B) 2 days

C) 3 days

D) 4 days

From question #1, what is the LF for Node D?

A) 18

B) 19

C) 21

D) 22

From question #1, what is the slack in node D?

A) 0 days

B) 1 day

C) 2 days

D) 4 days

From question #1, what is the ES for Node C?

A) 3

B) 4

C) 5

D) 6

We have a project (Cardinal), with these activities in days: Activity A with duration 4 and no precedents. Activity B with duration 15 and predecessor. A, Activity C with duration 9 and predecessor. A, Activity D with duration 2 and predecessor B, Activity E has duration 6 and predecessors B and C, Activity F has duration 4 and predecessor D, and Activity G has duration 15 and predecessors of E and F. Draw this to answer the following questions. How long is this project scheduled to take? 34 days 37 days 40 days 41 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!