Question: From the Earliest Completion Time, Table 1 9 . 1 4 , the total time for the project is expected to be 2 5 days.
From the Earliest Completion Time, Table the total time for the project is expected to be days. However, the calendar time is days.
Provide a short answer for each of the following below.
Place a line break between each answer.
A Please list, which are the tasks on the Critical Path?
B What are two examples where the grey activities were added?
C For what purpose does the team intend to use this slack grey tasks time? Why do you agree or disagree with this adjustment to the schedule?
D Why do you think that some activity is scheduled for the weekend? What type of activity is it
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
