Question: From the Earliest Completion Time, Table 1 9 . 1 4 , the total time for the project is expected to be 2 5 days.

From the Earliest Completion Time, Table 19.14, the total time for the project is expected to be 25 days. However, the calendar time is 33 days.
Provide a short answer for each of the following below.
(Place a line break between each answer.)
A. Please list, which are the tasks on the Critical Path?
B. What are two examples where the grey activities were added?
C. For what purpose does the team intend to use this slack (grey tasks) time? Why do you agree or disagree with this adjustment to the schedule?
D. Why do you think that some activity is scheduled for the weekend? What type of activity is it?
 From the Earliest Completion Time, Table 19.14, the total time for

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!