Question: Given is a CPM project network diagram as shown below. Activit y day Start Start 0 A 5 A B B 9 a) The
Given is a CPM project network diagram as shown below. Activit y day Start Start 0 A 5 A B B 9 a) The Project Completion time = Blank 1 days. C 4 C D b) The Earliest Start time, ES, of Activity G = Blank 2 days. c) The Latest Finish time, LF, of Activity C = Blank 3 days. D 7 E d) The critical activities are = Blank 4 (ex. Fill in the answer as: ABCD) E 4 F G F 8 H G 6 End H 8 End 0