Question: From the following Activity Definitions Table (down below), draw a Critical Path Method Network. Including early and late activity times, and slacks (total and free
From the following Activity Definitions Table (down below), draw a Critical Path Method Network. Including early and late activity times, and slacks (total and free floats). find the project completion time and highlight the critical path.
Please continue the CPM Network I have started below (pay attention to slacks/floats in the middle left and right box)




\fWBS Activity Name Activity Name Description Duration Predecessor Dependencies Lag Cost Level ID (Days) Name Relationship Lead Darwin Dingos Entire Process from Planning FC Launch to Club launch 2 A Registration of AFL Club Preparation & submission of registration documentation 1.1.1 Al Registration Fill out all registration forms 7 N/A $100 forms provided by the AFL board 3 1.1.2 A2 Submit Submit and pay registration 10 Al FS $1,500 registration fees with supporting form: document: 2 1.2 Obtain approval of registration 1.2.1 A3 Prepare for Prepare for registration 7 A2 FS -3 $500 presentation presentation to the AFL board 3 1.2.2 A4 Amouncement Notify all stake holders of 7 A3 FS N/A of Club approval for club registration Registration 2 Establishment of the Board of Directors & Development of the clubs business plan 2 2.1 Identify potential board members 3 2.1.1 BI Contact List of Contact the list provided by 14 A4 FS N/A potential board the AFL board of potential member board members 3 2.1.2 B2 Conduct Conduct interviews with 10 B1 -7 N/A interviews of potential board members potential board members 2 2 2 Appoint board members 3 2.2.1 B3 Develop a Form a short list from the 7 B2 N/A short list of initial interviews for the potential board board member positions members 3 2.2.2 B4 Conduct Undertake background 10 BE FS $200 background & checks and referee checks on referee checks short listed board members 3 2.2.3 B5 Appoint Board Appoint Board of Directors 4 B4 FS $1,000 of Directors from selected applicants 2 Development of Business Plan 2.3.1 B6 Outline Club's Outline the club's major 10 B5 0 N/A key policies & policies & guidelines guidelines3 2.3.2 B7 Develop club's Develop the club's budget 14 B6 FS $500 budget & and create an organisational organisation chart of staff club structure chart 3 2.3.3 Finalize Confirm business plan and 7 B7 FS 3 Business Plan receive endorsement from the Board of Directors 2 3 C Confirmation of 100 core sponsorships' partnership 2 3.1 Establish a short list of potential sponsors 3 3.1.1 Complete a Undertake a set of criteria 7 B8 FS -3 $100 multi-criteria assessment of likely sponsors assessment 3 3.1.2 C2 Conduct Organise and run meetings 10 CI FS 0 $1,000 meetings with with chosen sponsors potential sponsors 2 3.2 Secure Sponsorship: 3 3.2.1 C3 Develop Develop contracts for each 7 C2 FS -2 $200 sponsorship individual sponsor tailed to contracts their business company 3 3.2.2 CA Sign and Sign contracts and announce 14 C3 F3 0 $1,000 announce sponsorships to community sponsorships members, media, and AFL board 2 4 D Employment of Club Staff 2 Establish a short-list of preferred club staff 3 4.1.1 DI Develop job Create a detailed descriptions 7 0 NA descriptions under each job position 3 4.1.2 D2 Advertise job Advertise job positions on all 14 FS $2,000 positions recruitment platforms (e.g. geek, indeed) 3 4.1.3 Conduct Undertake interviews with D2 SS -3 NA interviews with chosen staff members based potential staff on experience, skills, and members mowledge 3 4.1.4 D4 Conduct Undertake background 12 D3 SS 2 $200 referee checks checks and referee checks on on chosen staff selected staff members and & notify notify chosen staff 3 4.1.5 DS Sign staff Sign contracts for each staff 7 D4 FS 0 $500 contracts member 2 5 E Development and execution of Marketing Plan 2 5.1 Develop the Marketing Plan 3 5.1.1 El Access and Evaluate and identify the 10 D5 FS 0 NA define target target market and audience p of potential memha3 5.1.2 Develop Determine the clubs 10 NA marketing marketing strategy strategy including goals, tacky, and timeline) 3 5.1.3 E3 Finalize Settle Marketing Plan and E2 FS $8,000 Marketing Plan receive endorsement from Board of Directors 2 5.2 Execution of Marketing Plan 3 5.2.1 E4 Design Plan and create 14 E3 FS 2 $1,000 Advertising advertisement promotional Materials materials (e.g posters, social media, brochures, ads) in line with Marketing plan 3 5.2.2 ES Launch Launch advertising 14 FS 0 $7,000 Campaign campaign in line with Marketing plan 2 F Membership Rollout 2 Develop membership tiers 3 6.1.1 FI Form Form membership 7 E5 FS 0 NA Membership levels/tiers and classify the Tiers benefits of each ties 3 6.1.2 F2 Determine Determine Membership fees 7 FI 1 NA membership for each level tier fee: Memberships open for purchase 3 6.2.1 F3 Prepare Arrange marketing materials F2 FS 0 $400 membership in lime with the club's marketing Marketing plan materials 3 6.2.2 F4 Present Present and receive FS $1,000 Marketing endorsement of membership Material tiers from Board of Directors 2 7 G Club Launch 2 7.1 Plan and execute launch event 3 7.1.1 GI Plan launch Plan club launch event 14 F4 FS 0 $30,000 event including venue. photography, catering, entertainment 3 7.1.2 Send Send invitations of launch F4 FS $2,000 invitations event out to sponsors, 14 community members and AFL committee 3 7.1.3 G3 Completion of Completion of Darwin G2 FS 0 NA Club Launch Dingos Football Club Launch Event
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts