Question: From the following information, develop a project network (you are not required to show the network). Use Day 0 as an early start for the
From the following information, develop a project network (you are not required to show the network). Use Day 0 as an early start for the first activity. A. Complete the forward and backward pass.
B. Compute activity slack.
C. Which activities represent the critical path? D.
How many days will the project take?
ID Predecessor Time A None 10 B A 8 C A 10 D B 12 E C 6 F D, E 8