Question: From the given data, draw the project network diagram using Activity-on-Arrow (AOA) logic, estimate the time of project completion, and define the critical path and

From the given data, draw the project network

From the given data, draw the project network diagram using Activity-on-Arrow (AOA) logic, estimate the time of project completion, and define the critical path and activities, early start (ES), early finish (EF), late start (LS), and late finish (LF) of the project. Analyze the possibility for the project to have slack and explain the situation. ACTIVITY PREDECESSOR DURATION A 8 B 13 C A 9 D A 4 E B 14 F F B 8 G D 3 H C,F,G 12 1 C, F, G 9 J E, H 10 7

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!