Question: From the given data, draw the project network diagram (with AOA logic), estimate the time of project completion, and define the critical path and activities

From the given data, draw the project network

From the given data, draw the project network diagram (with AOA logic), estimate the time of project completion, and define the critical path and activities of the project. Analyze the possibility for the project to have slack and explain the situation. ACTIVITY PREDECESSOR DURATION A 4 B A 3 A 2 D B N E C 6 F 3 G D, E 4 H F, G 6