Question: From the given network diagram below; 1. Compute the expected time for each activity and the expected duration for each path. 2. Determine the critical

From the given network diagram below;

1. Compute the expected time for each activity and the expected duration for each path.

2. Determine the critical path using PERT. Provide a table.

3. Compute the variance for each activity and the variance for each path.

4. Determine the probability that this project will be completed within 17 weeks of its start.

5. Determine the probability that the project will be computed within 15 weeks.

6. Redraw the network diagram with completes labels.

From the given network diagram below; 1. Compute

From the given network diagram below; 1. Compute the expected time for each activity and the expected duration for each path. 2. Determine the critical path using PERT. Provide a table. 3. Compute the variance for each activity and the variance of each path. 4. Determine the probability that this project will be completed within 17 weeks of its start. 5. Determine the probability that the project will be computed within 15 weeks 6. Redraw the network diagram with complete labels. 2-4-6 b b 1-34 2-3-4 e a d 3-4-5 g f 5-7-9 3-5-7 2-4-5 O h i 3-4-6 4-5-6 Optimistic time Probable time Pessimistic time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!