Question: From the Precedence Diagram Table, construct an Activity Network Diagram following the format per Activity Box. Do forward and backward to pass to identify the

From the Precedence Diagram Table, construct an Activity Network Diagram following the format per Activity Box.

Do forward and backward to pass to identify the critical path.

Identify the critical path.

From the Precedence Diagram Table, construct an

Duration Predecessor Activity A 5 B 7 A 2 A D 12 B E 20 B F 4 I TIM G 11 I 8 D 1 6 E J 3 E K 9 F L 1 H M 14 J Ez N 19 GI,K,L,M