Question: Problem 1 A project information is given in the following table: Task Predecessors Duration (weeks) None ABCDEEG F None None A,B,C D C,E C F,

Problem 1 A project information is given in the following table: a. Construct the activity network. b. List all paths with their time durations. c. Identify the critical path and the project completion time? robrem 2 A construction manager is responsible for developing a new site for residential home construction. He has identified the following activities, their predecessor activities, and their expected duration: 2. Draw the network diagram representing this project. b. Use the forward and backward pass method to label the network in full. Give a full schedule table (ES, BR, LS, LR, and slack) for cach activity. c. Identify the critical path. What is the project completion time