Question: From the project plan, we that a project has a total budgeted cost of $937,118 and a project completion time of 18 weeks. At the
From the project plan, we that a project has a total budgeted cost of $937,118 and a project completion time of 18 weeks. At the moment, the project has been in a performing stage. At the end of week 8, the project progress report shows that the project has consumed a total of $314,666, the project cumulative earned value is $358,460, and the project schedule performance index is 0.83.
What is the value of the project schedule variance at the end of week 8?
Use at least 4 decimals.