Question: Co Survey toring Question 4 From the project plan, we that a project has a total budgeted cost of $975,295 and a project completion time
Co Survey toring Question 4 From the project plan, we that a project has a total budgeted cost of $975,295 and a project completion time of 15 weeks. At the moment, the project has been in a performing stage. At the end of week 8, the project progress report shows that the project has consumed a total of $421,925, the project cost performance index is 0.88) and the project schedule performance index is 0.89. Looking at the project report at the end of week 8, what is the estimated project cost at completion if the project continues at the cost performance index of 1.0? Use at least 4 decimals. 15 pts Qu Qu Que Time Runnin Attempt due A 1 Hour, 8 M
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
