Question: From the provided table, determine the expected completion time ( in weeks ) for Activity D . Activity A M B Immediate predecessors A 1

From the provided table, determine the expected completion time (in weeks) for Activity D.
Activity A M B Immediate predecessors
A 123-
B 234-
C 456 A
D 8910 B
E 258 C, D
F 456 D
G 123 E