Question: table [ [ ACTIVITY , a , m , b , table [ [ Immediate ] , [ predecessors ] ] ] ,

\table[[ACTIVITY,a,m,b,\table[[Immediate],[predecessors]]],[A,1,2,3,-],[B,2,3,4,-],[C,4,5,6,A],[D,8,9,10,B],[E,2,5,8,C, D],[F,4,5,6,D],[G,1,2,3,E]]
From the provided table, determine the expected completion time (in weeks) for Activity D.
A.7
B.6
C.9
D.5.
 \table[[ACTIVITY,a,m,b,\table[[Immediate],[predecessors]]],[A,1,2,3,-],[B,2,3,4,-],[C,4,5,6,A],[D,8,9,10,B],[E,2,5,8,C, D],[F,4,5,6,D],[G,1,2,3,E]] From the provided table, determine the expected completion time