Question: Further to the data provided above for 3 estimates, the management is now contemplating to crash the network to the minimum possible time under the

  1. Further to the data provided above for 3 estimates, the management is now contemplating to crash the network to the minimum possible time under the crash cost scheduled provided overleaf. Answer(a)what would be theminimum durationof the project? And(b)what is the correspondingcrash cost? And(c )if the management wants to crash the project down to approximately29.85 weeksonly, what will be thetotal costincurred and corresponding crash schedule? You must submit computer outputs (original) for questions 5 and 6 to earn credit.