Question: g- The difference between being proactive and reactive is the development of a: A. Payoff table B. Range of probabilities C. Range of payoffs D.
g- The difference between being proactive and reactive is the development of a:
| A. | Payoff table | |
| B. | Range of probabilities | |
| C. | Range of payoffs | |
| D. | Contingency plan |
h- All of the following are factors in the assessment of project risk assessment except?
| A. | Risk event | |
| B. | Risk probability | |
| C. | Amount at stake | |
| D. | Insurance premiums |