Question: g- The difference between being proactive and reactive is the development of a: A. Payoff table B. Range of probabilities C. Range of payoffs D.

g- The difference between being proactive and reactive is the development of a:

A.

Payoff table

B.

Range of probabilities

C.

Range of payoffs

D.

Contingency plan

h- All of the following are factors in the assessment of project risk assessment except?

A.

Risk event

B.

Risk probability

C.

Amount at stake

D.

Insurance premiums