Question: Gantt Chart A change management process in a construction organization was quite elaborate. Before any change was approved to the construction plans, it had to
Gantt Chart
A change management process in a construction organization was quite elaborate. Before any
change was approved to the construction plans, it had to be thoroughly evaluated from a technical
perspective to receive an initial approval. If it passed that approval, it was evaluated from a cost and
schedule perspective for final approval. The list of all activities and the relationship between them is
provided below.
Create a Gantt chart and determine how long the change approval process normally takes. Assume
a five day work week and that all duration are given in workdays no weekends or holidays. You
can build this using project management software, or you can do a simple Gantt Chart using a
spreadsheet application such as Excel and allowing a column to represent a time interval, such as a
day.
# Activity Predecessor Duration
Receive change request and log into change management
system and assign number
none day
Preliminary review for completeness by Change Board Chair days
Review by engineering days
Review by purchasing days
Review by construction days
Review by safety days
Review by legal days
Review by Project Management days
Change Board meeting to make initial approval decision day
Create updated drawings and specifications days
Place purchase orders days
Determine reuse options for scrap or obsolete material days
Update construction schedule days
Calculate total cost and schedule impact days
Change Board meeting to make final approval decision dayGantt Chart
A change management process in a construction organization was quite elaborate. Before any change was approved to the construction plans, it had to be thoroughly evaluated from a technical perspective to receive an initial approval. If it passed that approval, it was evaluated from a cost and schedule perspective for final approval. The list of all activities and the relationship between them is provided below.
Create a Gantt chart and determine how long the change approval process normally takes. Assume a five day work week and that all duration are given in workdays no weekends or holidays. You can build this using project management software, or you can do a simple Gantt Chart using a spreadsheet application such as Excel and allowing a column to represent a time interval, such as a day.
table#Activity,Predecessor,DurationtableReceive change request and log into change managementsystem and assign numbernone, dayPreliminary review for completeness by Change Board Chair, daysReview by engineering, daysReview by purchasing, daysReview by construction, daysReview by safety, daysReview by legal, daysReview by Project Management, daysChange Board meeting to make initial approval decision, dayCreate updated drawings and specifications, daysPlace purchase orders daysDetermine reuse options for scrap or obsolete material, daysUpdate construction schedule, daysCalculate total cost and schedule impact, daysChange Board meeting to make final approval decision, day
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock