Question: Gantt Chart Case Study: Software Development Project Project Description: A tech company is working on a large software development project. The project involves designing, developing,
Gantt Chart Case Study: Software Development Project
Project Description:
A tech company is working on a large software development project. The project involves designing, developing, testing, and
deploying a new software application. The team is distributed across the USA, India, and Germany.
Project Duration:
Six months or weeks
Key Milestones:
Project Kickoff
Requirements Collection
Designing
Building
Testing
Launch
Project WrapUp
Team Distribution:
USA Team: Project Management, Design
India Team: Development, Testing
Germany Team: Requirements Gathering, Testing
Tasks and Timeline:
Week : Project Kickoff Week : Project Kickoff
Kickoff Meeting
Identifying Stakeholders
Initial Project Planning
Week : Requirements Collection
Conducting Requirement Workshops
Documenting Requirements
Reviewing and Approving Requirements
Week : Designing
Creating Design Specifications
Reviewing Design
Finalizing Design
Week : Building
Setting Up Development Environment
Developing Software Modules
Integrating Modules
Code Review
Week : Testing
Preparing Test Cases
Unit Testing
Integration Testing
User Acceptance Testing Week : Launch
Preparing Deployment Plan
Deploying Software
Providing PostDeployment Support
Week : Project WrapUp
Reviewing Project
Documenting Lessons Learned
Finalizing Project Report
Submission Guidelines:
The assignment should be developed in Excel and formatted appropriately.
Each task should be clearly labeled and organized.
The assignment should be submitted as a PDF document.
Use of any Al tools to complete the task is strictly prohibited.what each of these functions performs within a software development project PROJECT MANAGER PROJECT MANAGER ASSISTANT SOFTWARE DEVELOPERS SOFTWARE ARCHITECT BUSINESS ANALYST USER EXPERIENCEUX DESIGNERS USER INTERFACE UI DESIGNERS TESTER QA ENGINEER TECHNICIAN
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock