Question: During a period, 17 500 labour hours were worked at a standard cost of 6.50 per hour. The labour efficiency variance was 7800 favorable. Required
During a period, 17 500 labour hours were worked at a standard cost of £6.50 per hour. The labour efficiency variance was £7800 favorable.
Required
How many standard hours were produced?
Step by Step Solution
3.34 Rating (151 Votes )
There are 3 Steps involved in it
Solution To find the number of standard hours produced we need t... View full answer