Question: Given a BCWP of $ 7 3 , 0 0 0 , an ACWP of $ 1 0 0 , 0 0 0 , a
Given a BCWP of $ an ACWP of $ a BAC of $ and a BCWS of $ Calculate the schedule performance index SPI and identify if the project is ahead of schedule, on schedule or behind schedule
A This project is on schedule
B This project is behind schedule
C $ This project is ahead of schedule
D None of the above