Question: QUESTION 2 (25 marks) Table 2 shows the cost status at the end of the fourth month (cost in thousands): SUBTASKS 1 2 3 4

QUESTION 2 (25 marks) Table 2 shows the cost

QUESTION 2 (25 marks) Table 2 shows the cost status at the end of the fourth month (cost in thousands): SUBTASKS 1 2 3 4 5 6 7 8 TOTAL Table 2: Cost Status STATUS BCWS Completed 100 Completed 50 Completed 50 Not Started 70 Completed 90 Not Started 40 Started 50 Not Started BCWP 100 50 50 0 90 0 50 ACWP 100 55 40 0 140 0 25 a. Determine the progress and cost status for EACH of the subtasks. (17 marks) b. Where BAC is the value of BCWS at completion = RM579.000. Estimate the cost at completion for Task 3. (8 marks)