Question: - Given: a Cost Plus Incentive Fee (CPIF) project you are managing: - Target cost: $100,000 Actual cost: $80,000 Target fee: $20,000 Maximum fee: $25,000
- Given: a Cost Plus Incentive Fee (CPIF) project you are managing:
- Target cost: $100,000 Actual cost: $80,000 Target fee: $20,000 Maximum fee: $25,000 Minimum fee: $15,000 Sharing ratio: 60/40
How much fee would the contractor earn?
What should be the final price of the contract?
Step by Step Solution
3.36 Rating (159 Votes )
There are 3 Steps involved in it
To calculate the fee the contractor would earn in a Cost Plus Incentive Fee CPIF project we need to ... View full answer