Question: Given a particular project with typical duration of 40 weeks. Due to various factors, the project could be done in 30 weeks as the best
Given a particular project with typical duration of 40 weeks. Due to various factors, the project could be done in 30 weeks as the best case, but in the worst case situation, the project could take up to 80 weeks. What is the average project duration that should be used in project planning? Show your calculations.