Question: Given a precedence network for small project. Find: All times in the box. Project duration Critical path [1]ES = Max(all) Initial Time EF + FS

Given a precedence network for small project. Find: All times in the box. Project duration Critical path [1]ES = Max(all) Initial Time EF + FS ES + SS EF + FF-D ES + SF-D Terminal Time LS - FS [3]LF = Min(all) LF - FF LS-SS +D FF = Min(all LF - SF +D [4]LS = LF-D (ES, - EF - FS ES - ES -SS, EF - EF - FF, EF - ES - SF, [2]EF = ES +D Note: ZZ SS,FF 10 8 SF 6 B D FS 5 SS 4 FF 6 12 14 16 4 ZZ 3,6 E F H SS 4 FF3 22 5 SS 11 G