Question: Given a project WBS as shown on the right, you are required to: 1.Sequence the work packages (use work packages in the first two levels
Given a project WBS as shown on the right, you are required to:
1.Sequence the work packages (use work packages in the first two levels of WBS, do not show any activity)
2.Sequence activities under site work package
3.Sequence activities under site security package
4.Sequence activities under structure package
5.Develop the sequence of the whole project
6.Develop precedence diagram and determine project duration
7.Re-sequence activities given that activities cannot be done concurrently due to space limitation
Project WBS
Site work
Drainage (1d)
Grading (1d)
Paving (2d)
Landscaping (4d)
Site security
Fencing (3d)
Security lights (1d)
Structure
Exterior
Slab-on-grade (5d)
Concrete masonry unit (CMU) walls (8d)
Roof (5d)
Roll-up doors (1d)
Bar joists (3d)
Interior
Electrical (3d)
Finishes (4d)
Ceiling (2d)