Question: Given: activity A is a starting activity. A is the pre-requisite of E and D F followed right after B G can only start once
Given:
activity A is a starting activity.
A is the pre-requisite of E and D
F followed right after B
G can only start once D and F have been accomplished
K is an ending activity which followed by B and H, respectively
I is also a prerequisite of K
C precedes L
L is an ending activity
J is and ending activity which happens to be the successor of activities E and G
A - 12
B - 12
C - 25
D - 20
E - 23
F - 8
G - 11
H - 25
I - 8
J - 18
K - 15
L - 30
Draw the Diagram and identify the critical path